Taiwan AI Data Centers & Development Projects

Explore published and rumored compute projects, location precision, capacity definitions and original sources.

Catalog coverage: 150 records. This is not an exhaustive national inventory or an operational-capacity total.

GUISHAN AI DATA CENTER

Public development intelligence

A publicly announced collaboration involving Taiwan Mobile, GMI Cloud and Vantage. Announced scale: approximately 7,000 NVIDIA Blackwell Ultra GPUs on GB300 NVL72, across 96 racks. Total power capacity is 25 MW; IT load is 16 MW. These figures are different measures and must not be added. Announced equipment is not live rental inventory or proof that all GPUs are operational.

VISIONBAY.AI KAOHSIUNG AI CLUSTER

Public operational intelligence

Public operational intelligence for Visionbay.ai in Kaohsiung’s Asia New Bay Area. Announced cluster capacity and utilization figures follow their individual source dates; they are not a live availability feed. The public information identifies the area, not an exact data hall or entrance.

TONGXIAO AICC DEVELOPMENT

Power application · Owner update

100 MW is a two-phase supply plan: 30 MW planned for 2029-06-20, followed by an additional 70 MW on 2030-02-20. The owner’s latest update places the project at the power-application stage. The supplied 2026-07-31 Taipower letter includes validity, works, inspection and contract conditions; it is not proof of 100 MW currently available. Backup capacity must not be added to regular supply. Planned wind, solar, storage and gas facilities in the applicant’s concept are not verified assets or an achieved RE100 commitment.

MEDIATEK TONGLUO R&D DATA CENTER

Partly operational · Phase 1 opened

MediaTek announced the opening of Phase 1 on 2026-05-07. News reports cite 15 MW for Phase 1 and 45 MW across three phases. The 45 MW plan includes Phase 1: do not add them or describe all 45 MW as operational. This is an internal R&D facility; external rental availability is unconfirmed.

PHISON ZHUNAN DATA CENTER PLAN

Power application · Owner update

Public acquisition records more strongly support the former Taiwan Imperial Tobacco facility at No. 8, Qunyi Road, Zhunan. The owner reports a power application; MW is undisclosed. A 2026-05-08 filing republication lists an NT$2.05 billion property transaction, and a 2026-09-11 report links the site to an AI data center plan. A separate 2026-09-09 report names Taiwan Tobacco and Liquor and NT$1.65 billion; these conflicting descriptions must not be merged. Existing Phison AI servers elsewhere are not equipment at this planned site.

DAYUAN AIDC DEVELOPMENT LEAD

Power application · Owner lead

The 30 MW figure and a location beside Dayuan Cogeneration come from the platform owner, who reports a power application. The power plant’s official address is only a surrounding-area reference. It does not verify the AIDC parcel, a partnership with the plant or approved capacity. Group-level AIDC news dated 2026-08-17 is background, not evidence for this site’s 30 MW.

BEIGANG AIDC POWER APPLICATION

Power application only · Owner lead

The owner clarifies that this project is only at the power-application stage. The 100 MW scale is owner-reported; the application, reference number, approved capacity and energization schedule have not been checked against documents. The 2026-09-09 land-transaction reporting is background, not evidence of AIDC construction or operation. The former Wanyou paper site and the whole Beigang industrial park must not be treated as one completed data center.

HUKOU RITEK CAMPUS AIDC LEAD

Power application · Owner lead

The 3 MW scale and the relationship between Clouded Leopard and RITEK’s Hukou campus come from the owner, who reports a power application. The campus can be referenced publicly, but the actual building, partnership and GPU inventory are unverified. No independently cross-checked announcement links this site, Clouded Leopard and 3 MW together.

CHIAYI TAIBAO AIDC CONVERSION LEAD

Project stage unconfirmed

The 70 MW scale and conversion of the former Makro property come from the owner. The historical address is in Taibao, Chiayi County; the project stage remains unconfirmed. This is a separate record from FCFC’s 70 MW Xingang lead. The old factory registration confirms an address, not an AIDC conversion, capacity or current ownership. Historical logistics recruitment at the address requires further handover and occupancy checks.

WISTRON GUIREN COMPUTING CENTER

Power application · Owner update

The main card uses a 10 MW plan consistently reported by multiple sources on 2026-07-30 and in subsequent August coverage. A 2026-07-31 Economic Daily report separately cites 100 MW; no company document has resolved that discrepancy, so it is not labeled a confirmed typo. The owner reports a power application. Two-stage power delivery does not mean either or both stages are energized; stage-level MW and exact dates are undisclosed.

FCFC CHIAYI XINGANG SITE

Existing buildings · Power availability under review

The owner reports a 70 MW development lead involving existing buildings at FCFC’s Xingang site, with power availability still being confirmed. Existing industrial supply or captive generation is not proof that 70 MW can be allocated to an AIDC. Reporting dated 2026-06-03 supports factory-space marketing for AI centers at Xingang and Longde, but not approved power for this specific lead. This is distinct from the 70 MW former-Makro project in Taibao.

FCFC LONGDE SITE

Existing buildings · Power availability under review

The owner corrected this lead to 70 MW. It concerns existing buildings at FCFC Longde, with power still under review. Existing factory supply or captive generation does not establish AIDC approval, energization or rentable capacity. News supports asset-reuse background, not approval of 70 MW. Do not merge this record with other FCFC sites, Lize compute projects or on-site generating facilities.

CMFC DASHE SITE

Existing buildings · Power availability under review

The owner reports a 10 MW lead at existing buildings at CMFC Dashe, with power under review. Corporate AI-transition reporting is background and does not verify this capacity, a tenant or commercial operation. CMFC is not CPDC or another neighboring Dashe company. Existing industrial or cogeneration capacity must not be treated as available AIDC capacity.

TATUNG DAYUAN AI DATA CENTER PLAN

Planning / POC preparation · Stage unconfirmed

Public reports link Tatung’s Taoyuan AI data center planning to its Dayuan factory and mention collaboration discussions and POC preparation. Capacity, power application, construction, energization and rental inventory are undisclosed. Reports dated 2025-11-10 and 2026-09-14 provide planning context. A factory registry status of operating concerns the existing factory, not the proposed AI data center.

ASUS TAOYUAN PRIVATE AI DC PLAN

Planning intelligence · Site and stage unconfirmed

Reporting dated 2026-09-14 confirms only a planned ASUS-owned AI data center in Taoyuan. A public address exists for the Luzhu factory, but the smart factory, AI LAB and proposed AI DC may be different facilities. The relationship requires official cross-reference. Capacity, the precise site and the power-procurement stage remain undisclosed.

CPDC TOUFEN AI COMPUTE CENTER PLAN

Collaboration planning · Stage unconfirmed

CPDC plans to reuse its Toufen plant for AI compute. The 2026-09-17 MoneyDJ report gives 5 MW for Phase 1 and a 50–100 MW Phase 2 plan; Phase 3 scale is undisclosed. These are plans, not energized or rentable inventory. Collaboration is still being developed. Reported customer demand does not establish named buyers, signed contracts, equipment counts or opening dates. Existing feeders, generation and cooling do not prove power approval for the AIDC.

YFY NANKAN 3 MW AI COMPUTE SITE LEAD

Existing property rental lead · Stage unconfirmed

A public rental listing at No. 275, Section 1, Nankan Road advertises 3 MW of power and markets the property for AI compute. The owner identifies it as YFY’s Nankan campus. Historical directories support the YFY name, while current government factory records identify Chung Hwa Pulp at the address; ownership and power-contract responsibility are not resolved here. The 3 MW property claim is not verified IT load, energized AIDC supply or GPU inventory.

SIGNALPRO XINSHI AI FACTORY

Power application · Owner-reported

The project scale is 6 MW, with approximately 1 MW of cooperation with GMI Cloud, according to information supplied to the platform. These figures have different scopes and must not be added together. The partnership is public; reporting describes 72 HGX B300 systems, without confirming their full allocation to this factory or commissioning.

GIGA COMPUTING GAIFA · TUCHENG

Public validation site · Commercial status unconfirmed

Giga Computing’s GAIFA in Tucheng is a compute and infrastructure validation site. Reported plans include 700 kW (0.7 MW) and six compute, storage and networking racks, with direct liquid cooling. GPU count, IT load, rental inventory and street address are undisclosed.

FENGCHI SHENGANG AIDC

Power application submitted

Provider-reported 9.9 MW project in Shengang, Taichung. A Taipower application has been submitted; approval has not been verified. Received on 2026-10-08; not independently verified. Total power and IT load are not separately disclosed.

SINGAPORE DEVELOPER NEIHU AIDC

Building under construction

Provider-reported 10 MW project in Neihu, Taipei. An unnamed Singapore company is constructing a five-storey building on its own land; power and commissioning status are undisclosed. Received on 2026-10-08; not independently verified. Total power and IT load are not separately disclosed.

FENGCHI LUZHU AIDC

Power application in progress

Provider-reported 50 MW AIDC project in the Luzhu science park area of Kaohsiung. A power application is in progress. Power approval, site address and IT load have not been independently verified.

PINGTUNG JIAYI POWER LEAD AIDC

Reported power-application outcome · Unverified

A provider reports an unnamed company obtained a 55 MW power-application outcome associated with Jiayi Substation in Pingtung. No Taipower document has been reviewed; approval terms and energization remain unverified. The suggested Daqing industrial area location is a provider hypothesis, not a confirmed site.

SOFTBANK TOMAKOMAI AI DATA CENTER

Under construction

SoftBank confirms construction in Tomakomai, targeting service in fiscal 2026. Over 300 MW is a long-term planned scale, not commissioned capacity.

SOFTBANK OSAKA SAKAI AI DATA CENTER

Announced development

SoftBank acquired former Sharp property for an approximately 150 MW power-receiving plan, potentially expanding beyond 250 MW. A target date is not commissioning evidence; this is separate from KDDI’s Sakai project.

KDDI OSAKA SAKAI AI DATA CENTER

Operational

KDDI opened its Osaka Sakai AI facility on January 22, 2026, reusing Sharp facilities and deploying systems including GB200 NVL72. MW is undisclosed in this source; GPU cloud trials and applications follow separate schedules.

FIRMUS ST LEONARDS AI FACTORY

Under construction

ABC reports construction of Firmus’s AI factory in St Leonards, Launceston. National program capacity is not assigned to this site.

FIRMUS WESLEY VALE AI FACTORY

Development application

ABC reports a development application for Firmus’s Wesley Vale facility. Completion and operation are not established by the reviewed source.

FIRMUS BELL BAY AI FACTORY

Local development approval

ABC reports local development approval for the 288 MW Bell Bay project. Firmus says energy arrangements remain to be finalized; approval is not energization or operation.

NEXTDC / OPENAI SYDNEY S7

MOU / planned

NEXTDC and OpenAI signed an MOU for an AI campus at S7 in Eastern Creek, Sydney. The announcement’s 550 MW potential capacity is not operational supply.

STARGATE ABILENE

Partly operational / expanding

OpenAI confirms early training and inference at Abilene. Expansion plans are separate from existing operations; total Stargate capacity is not allocated to this campus.

STARGATE SALINE TOWNSHIP / THE BARN

Under construction

Oracle and Related Digital confirm construction of The Barn in Saline Township, Michigan. This record does not infer MW or GPU availability.

STARGATE PORT WASHINGTON / LIGHTHOUSE

Announced development

Vantage announced four Lighthouse data centers in Port Washington, targeting close to 1 GW and completion in 2028. These are announced plans, not proof of current operation.

SAKURA ISHIKARI GPU CAMPUS

Operational

AI infrastructure with approximately 1,100 Blackwell GPUs has entered operation; this is not available rental inventory.

MIYAGI AI DATA CENTER

Operational

Opened July 31, 2026 for GPU server colocation. MW is undisclosed.

AI FUKUSHIMA GPU CAMPUS

Building completed; operation separately verified

The company lists building 1 completed in September 2024 and building 2 in February 2025. Phases are grouped without double-counting capacity.

MODULE DPDC FUKUSHIMA

Building completed; operation separately verified

Modular AI facility completed in May 2026. Completion does not establish rental inventory or utilization.

YUZAWA GX DATA CENTER

Operational

The official service page describes operating container facilities in Yuzawa. Product specifications are not total campus capacity.

HIGHRESO SHIKA GPU CAMPUS

Operational

The first center began operating in 2019; the second opened in August 2022. Regional phases are grouped.

HIGHRESO TAKAMATSU GPU CENTER

Operational

Opened in December 2024 through conversion of an existing research facility.

HIGHRESO AYAGAWA GPU CENTER

Operational

Opened March 3, 2026 using the former Ayakami junior high school facilities; capacity from other campuses is excluded.

HIGHRESO GENKAI GPU CENTER

Operational

GPU center converted from a former school, operating since August 2025.

NTT KEIHANNA OSK11

Operational

The opening announcement describes a 30 MW facility. Facility capacity is not owned GPU capacity or rental inventory.

QUANTUM MESH TAKAHAMA DRIP 1

Operational

Operating since December 1, 2024. Immersion-cooled edge infrastructure, not a large GPU training campus.

NTT-ME ISHIKARI AI CONTAINER VILLAGE

Planned / development

Groundbreaking ceremony held May 18, 2026; the city lists a June construction target and operation as early as February 2027. Operation is unconfirmed.

ISHIKARI RENEWABLE DC 1 / GMO GPU

Planned / development

GMO plans a GPU deployment within an existing data hall by end-2026. This is a tenant deployment, not an additional standalone new building.

J-POWER KAMINOKUNI GPU CENTER

Planned / development

Project implementation approved by the company, with compute services targeted for summer 2027.

FANTASISTA SENDAI AI DEVELOPMENT

Planned / development

Planned receiving capacity of 200 MW; phase 1 targets development permission in fiscal 2028, not commissioned capacity.

AKITA S2 / BITGRIT AI PROPOSAL

Planned / development

Proposal targets operation in the early 2030s. This is not the Tohoku Electric former thermal plant site; exact premises remain unverified.

AKITA FORMER POWER SITE DC PROSPECT

Tenant recruitment / site evaluation

Candidate site with potential for a 1 GW-scale cluster, under tenant discussions. Not approved or operating capacity, and separate from the S2 proposal.

JERA CHIBA AI INFRASTRUCTURE

Planned / development

MOU and feasibility stage, up to 400 MW, targeting operation around 2028.

NTT INZAI SHIROI CAMPUS GROUP

Planned / development

Phased expansion targets 250 MW of IT capacity across the area, not one building.

NTT TOCHIGI TCG11

Planned / development

Completion planned in 2029, ultimately around 100 MW IT capacity; approximate Tochigi industrial park locality.

NTT CENTRAL TOKYO LIQUID-COOLED AI DC

Under construction

Construction announced; service targeted for the second half of fiscal 2029. Only central Tokyo is disclosed, not a street address.

NTT / TEPCO OTA CONTAINER DC PARK

Under construction

Construction initiative and applications announced for liquid-cooled GPU facilities; full operation is unconfirmed.

GIGASTREAM NANTO CAMPUS PROPOSAL

Planned / development

City-confirmed public-private campus proposal. Planned scale is not currently available capacity.

OPTAGE MIHAMA AI CONTAINER DC

Planned / development

Announcement targets opening in fiscal 2026. No confirmed commissioning evidence; not automatically classified as operational.

UBITUS MAIZURU AI DATA CENTER

Planned / development

Siting agreement for Taira industrial estate, completion targeted for 2027; about JPY18 billion investment, MW undisclosed.

JR KYUSHU KURUME MODULAR DC

Planned / development

Construction plan targets completion in March 2027; colocation for cloud and AI, not an inventory of installed GPUs.

DAYONE IMARI CAMPUS

Planned / development

Planned 200 MW campus targeting 2030; the report separately identifies land with 160 MW secured power. These figures must not be added.

KAISHIN CIRCULAR PARK KYUSHU

Planned / development

Siting agreement signed July 18; demonstration followed by phased growth to a cumulative 350 MW, not rental inventory.

Microsoft Fairwater Mount Pleasant

Operational (stated phase only)

Microsoft confirmed its first facility operational on June 23, 2026. The adjacent second facility remains under construction, targeting 2028.

Meta Tulsa AI Data Center

Under construction

Meta announced groundbreaking in April 2026 and an investment exceeding US$1 billion. Site MW is not disclosed in this source.

SB Energy / OpenAI Milam Campus

Under construction

The current developer page lists construction and approximately 750 MW; January 2026 reporting cites 1.2 GW. Scope/basis reconciliation is pending; do not add the figures or treat them as rental inventory.

Stargate Shackelford County

Planned

The September 2025 announcement confirms this site in the development program. Current commissioning is not verified; no allocation of aggregate Stargate capacity.

Stargate Doña Ana County

Planned

The September 2025 announcement confirms this site in the development program. Current commissioning is not verified; no allocation of aggregate Stargate capacity.

Stargate Lordstown

Under construction

The September 2025 announcement confirms this site and groundbreaking. Current commissioning is not verified; no allocation of aggregate Stargate capacity.

Bell AI Fabric Sherwood

Under construction

The October 1 government update confirms construction of the 300 MW campus and four first-phase shells. First hall targets H1 2027; potential 1.2 GW expansion is not built capacity.

Meta Sturgeon AI Data Centre

Under construction

Meta announced its Sturgeon County campus in July 2026 with a published 1 GW scale and groundbreaking. This is not commissioned capacity.

TELUS / Westbank Kamloops

Planned

May 2026 announcement: targeted later in 2026. The over-150 MW goal for 2032 belongs to the three-site cluster, not this site. New commissioning evidence was not verified.

TELUS / Westbank Vancouver M3

Planned

May 2026 announcement: targeted to open at end-2026 and scale through 2028. The over-150 MW goal for 2032 belongs to the three-site cluster, not this site. New commissioning evidence was not verified.

TELUS / Westbank Vancouver 150 West Georgia

Planned

May 2026 announcement: targeted to come online in 2029. The over-150 MW goal for 2032 belongs to the three-site cluster, not this site. New commissioning evidence was not verified.

Ada London Docklands

Under construction

First building broke ground on February 26, 2026. Three 70 MW buildings are planned for 210 MW total; the first targets mid-2028 service.

Pure DC Brent Cross LON01

Under construction

Final major build phase began in September 2026; campus total is planned at 90 MW and B2 completion targets Q2 2029. Not all campus capacity is complete.

QTS Cambois Campus

Under construction

Former power-station redevelopment near Blyth. QTS lists earthworks and first-building construction plans in 2026; subsequent work remains subject to permissions.

Stargate UK Cobalt Park

Paused / delayed

Stargate UK was reported paused in April 2026. This marker retains its announced Cobalt Park area and does not imply other facilities there stopped operating.

Nscale Loughton AI Project

Paused / delayed

September 24, 2026 reporting identifies power-related delays; delivery timing remains uncertain.

Equinix Dublin DB7x

Under construction

Construction announced March 20, 2026. The facility supports AI and enterprise workloads; retail capacity targets early 2028 using already allocated power.

Zerra Western Downs Digital Park

Permit application

Up to 1.44 GW planned IT capacity across four stages; development application under assessment. The developer cites an Anthropic lease commitment; capacity is not operational.

Zerra Campbellfield Project Dune

Permit application

Former Ford property redevelopment proposes approximately 336 MW of power capacity across six stages; under assessment.

Datagrid Makarewa AI Factory

Consent granted / development

Resource consents obtained March 2026. 240 MW is IT capacity; the developer describes 280 MW total power consumption. Do not add them or equate consent with operation.

Contact / CDC Stratford Proposal

Planned

August 10, 2026 proposal explores 250 MW IT load near the retired TCC plant. Neither party has committed to construction; tenants, finance and approvals remain conditions.

Nxera DC Tuas

Operational (stated phase only)

Opened February 9, 2026 with 58 MW AI-ready capacity. More than 90% was committed before launch; this is not available rental inventory.

Google Visakhapatnam AI Hub

Under construction

Groundbreaking at Tarluvada on April 28, 2026. The gigawatt-scale hub comprises three campuses; this is one cluster anchor and does not duplicate aggregate capacity.

Zerra Navi Mumbai

Consent granted / development

Planned 240 MW IT capacity on a 29-acre site. Developer reports initial development consents, not all approvals or commissioning.

Cassava Cape Town AI Factory

Deployment / testing

May 4, 2026 reporting describes initial deployment in place and services preparing to go live. Subsequent full commissioning was not verified.

Cassava Johannesburg AI Factory Plan

Planned

May 2026 interview describes a planned AI factory using an existing footprint with room for a 20 MW installation, not 20 MW of delivered compute.

Meta El Paso AI Campus

Under construction

July 2026 announcement confirms construction, planned 1 GW and first delivery targeted in 2028. Meta is the initial sole occupant; not rental inventory.

Meta Hyperion Richland Parish

Under construction

July 2026 update expands the announced scale to 5 GW. Construction is underway; this is not 5 GW of commissioned capacity.

Hut 8 River Bend

Under construction

Developer lists 245 MW contracted IT capacity supported by 330 MW utility capacity. Commercialization is not delivery; full commissioning is not verified from this page. An October 7 report confirms construction.

AWS Homer City Campus

Permit application

October 2026 report describes a filed preliminary plan for 36 buildings, phased from late 2026 toward 2036. The adjoining 4.5 GW power plant is not site IT capacity.

Aligned Project Phoenix

Under construction

September 2026 report confirms groundbreaking of a published 2 GW, three-facility campus. Power-station redevelopment capacity is kept separate.

Beetaloo Weddell Proposal

Planned

Land reservation enables feasibility work on a 185-hectare proposal. The stated 2 GW power requirement remains subject to finance and major approvals.

Gingerah Project Meridien

Planned

April 2026 proposal describes an initial 240 MW IT phase, potential 1 GW expansion and a 2032 target. Environmental studies remain ahead; marker illustrates the broad region south of Broome.

HyperDC Moorabool MBL1

Permit application

September 2026 planning application proposes 400 MW IT capacity at 715 Ballan Road. Application is not approval or operation.

NEXTDC SC2 Sunshine Coast

Under construction

June 2026 local reporting confirms construction of a five-storey facility. Site MW is not inferred.

AirTrunk JHB3 / JHB4 Cluster

Planned

Two announced campuses together exceed 280 MW IT. One cluster marker avoids counting 280 MW per site or treating the four-campus 700 MW platform as fully operational.

YTL / JLand Sedenak Tech Park West

Planned

August 2026 announcement describes a gigawatt-scale new campus and land arrangement. The separate Kulai 1.2 GW figure is not assigned to this site.

Empyrion MY1 Nusajaya

Under construction

First 40 MW phase topped out in August 2026 and remains under construction, with service now targeted for Q1 2027. Over 200 MW is the multiphase campus target.

Google Elmina Data Centre

Under construction

October 2024 report confirms groundbreaking. Its 2026 completion target is not treated as proof of commissioning.

Tera Eco Business Park 7

Planned

September 2026 reporting identifies a conditional purchase of 221.665 acres for an AI-ready campus. It does not establish completed acquisition, construction or commissioning.

Digital Edge / B.Grimm BKK1

Under construction

Groundbreaking took place in September 2025. May 2026 financing supports the 100 MW campus targeting Q4 2026 delivery; commissioning is not verified.

DayOne Chonburi Tech Park

Under construction

Developer describes CTP1/CTP2 under development with a 300 MW scale and a separate 1 GW power-platform ambition. A 2026 RFS target is not commissioning evidence.

Empyrion TH1 Bangna

Under construction

Thai September 2026 reporting confirms construction, 20 MW IT and a Q3 2027 service target in the Udom Suk / Bang Na area.

Firmus / DayOne Batam AI Campus

Planned

June 2026 announcement describes a 360 MW NVIDIA DSX campus collaboration with phased deployment targeted from 2027, not operational capacity.

NeutraDC Cikarang Expansion

Planned

August 2026 power-cooperation MOU with PLN cites 200 MW. Total-versus-incremental wording requires clarification; an MOU is not a power approval.

BDx Jatiluhur AI Campus 2

Paused / delayed

Groundbreaking for a published 640 MW campus was announced September 22. September 30 reporting confirms a pause pending environmental and building approvals. Both milestones are retained.

AIC / Kinh Bac Tan Phu Trung

Planned

March 2026 MOU and application describe an initial 50 MW and about 28,000 GPUs, targeting April groundbreaking. Actual subsequent groundbreaking is not verified here.

SAIGONTEL Nam Tan Tap AI Proposal

Planned

An August 28, 2026 LOI proposes 200 MW IT, with an initial 100 MW phase. Power arrangements and investment procedures remain pending; the event date is distinct from an unconfirmed publication date.

VITRO Santa Rosa

Operational (stated phase only)

Government reported the launch of the 50 MW AI-ready facility in April 2025. Facility scale does not establish available rental inventory.

erex / KPS Pursat Feasibility Study

Planned

Government approval in July 2026 enables feasibility study and investment, announced in August. Site MW is undisclosed; the referenced 170 MW belongs to generation projects.

Silicon Tech Park Laos AI Feasibility

Planned

May 2025 MOU covers AI infrastructure feasibility and a potential 150-plus-hectare zone in the Vientiane capital area. It is not an approved or built data center.

Equinix SG6

Under construction

Groundbreaking in November 2024; 20 MW and a Q1 2027 target. Marker represents the city-state only; district or premises are not verified from the primary source.

Schwarz Digits Lübbenau

Under construction

Groundbreaking on former power-plant land in November 2025; site MW not established.

KIT AI Data Center

Planned

Planned initial electrical load 2 MW with connection up to 10 MW; first computers target 2030.

Sesterce Kaipola AI Campus

Planned

Former paper-mill proposal: 200 MW initial and 600 MW full campus, not operating capacity.

Nscale Kvandal KNB4–6

Under construction

Three contracted buildings total 100 MW under development, not the full Stargate campus scale.

EcoDataCenter / Mistral Borlänge

Planned

AI infrastructure partnership targets 2027; site MW not established.

Data Center Konin

Planned

Power letter of intent signed; construction targets early 2027, with up to 100 MW initial IT load.

Driver AI Luna

Planned

Public proposal describes 80 MW in four 20 MW units; not commissioned.

Serbia State Data Centre

Operational (stated phase only)

Government announced new modules and a supercomputer in service; 14 MW describes facility power, not rental GPU inventory.

Dutch AI Factory Groningen

Planned

Supercomputer planned at Zernike Campus in early 2028; the separate Niemeyer expertise centre is not this data-center location.

HUMAIN / DataVolt OXAGON

Under construction

Initial 100 MW under development within a 360 MW phase; long-term 1.5 GW ambition is not commissioned capacity.

CloudHQ Leopoldsdorf

Permit application

Three-building proposal with 150 MW connection scale remains subject to environmental review; GPU configuration not confirmed.

CRA Prague Gateway DC

Under construction

Groundbreaking and 26 MW power announced; potential AI Gigafactory use is not a confirmed award.

DDC1 Esbjerg

Under construction

Initial 11.5 MW phase broke ground, targeting October 2027; not live capacity.

Akur Capital Bakki

Planned

Proposed 100 MW project remains in AI tenant and power talks; construction is conditional.

Arnes Maribor AI / HPC Centre

Under construction

Foundation stone laid in May 2025; construction status reflects that source, with later commissioning unverified.

Khazna Ankara

Planned

Land secured for up to 100 MW; initial cloud infrastructure can adapt for AI, not commissioned.

Beyon Data Oasis

Operational (stated phase only)

First white-space facility commissioned for AI and cloud use; marker is a broad southern-Bahrain illustration.

MERLIN / EDGED Botorrita WIND

Planned

Planned 144 MW IT load targets H2 2029; strategic-investment designation does not equal all building permits.

Nebius / Greenergy AI Factory

Planned

August 2026 page describes a 22 MW deployment plan, not verified commissioning; exact publication day unavailable.

LitAI / LRTC VDC3

Planned

EuroHPC identifies LRTC VDC3 in Vilnius for the AI system; site MW not disclosed.

Mistral Bruyères-le-Châtel

Planned

March 2026 financing announcement planned 13,800 chips; a scheduled opening is not commissioning evidence.

Eni / Khazna AI Campus

Planned

Heads of terms propose a phased 500 MW IT campus, not completed financing, construction or commissioning.

PERUN Supercomputer

Operational (stated phase only)

Inaugurated in April 2026 as research HPC/AI infrastructure; rental capacity is not inferred.

Aqaba Digital Hub / Klstrai

Operational (stated phase only)

AI platform operational; 12 MW refers to the wider hub, not the platform GPU allocation.

Google Kuwait · South Al Mutlaa

Under construction

Government reports construction at three locations; this is one area anchor, with MW and GPU allocation undisclosed.

Google Kuwait · Jaber Al Ahmad

Under construction

Government reports construction at three locations; this is one area anchor, with MW and GPU allocation undisclosed.

Google Kuwait · Sulaibiya

Under construction

Government reports construction at three locations; this is one area anchor, with MW and GPU allocation undisclosed.

Switch Lanaken

Planned

Former paper-mill data-center proposal; tenants and AI hardware are not confirmed.

DAEDALUS Supercomputer

Under construction

Implementation launched in March 2025; the early-2026 target is not evidence of completion.

Pantheon AI Campus

Planned

Energy letter of intent relates to a proposed 1 GW project targeting 2027 construction, not approved or live capacity.

Cyta / RedMax Latsia Expansion

Planned

Acquisition and expansion of an existing facility; first expanded phase targets early 2027, without reclassifying existing operations.

Ooredoo Salalah

Operational (stated phase only)

Opened in August 2025 with 125 initial racks; 500 racks is a future expansion target.

MeluXina-AI · Bissen

Planned

July 2026 contract covers 1,008 GPUs across two sites without per-site allocation; scheduled autumn installation is not confirmed completion.

MeluXina-AI · Bettembourg

Planned

July 2026 contract covers 1,008 GPUs across two sites without per-site allocation; scheduled autumn installation is not confirmed completion.

CSCS Alps

Operational (stated phase only)

Research AI/HPC supercomputer inaugurated in September 2024; original historical date retained.

BRAIN++ / Discoverer++

Planned

Government announced Sofia Tech Park deployment with construction planned for 2026; new commissioning evidence was not established.

Start Campus SINES

Operational (stated phase only)

SIN01 has 37.5 MW live; planned 200 MW SIN02 and full 1.2 GW campus are not commissioned capacity.