A publicly announced collaboration involving Taiwan Mobile, GMI Cloud and Vantage. Announced scale: approximately 7,000 NVIDIA Blackwell Ultra GPUs on GB300 NVL72, across 96 racks. Total power capacity is 25 MW; IT load is 16 MW. These figures are different measures and must not be added. Announced equipment is not live rental inventory or proof that all GPUs are operational.
Public operational intelligence for Visionbay.ai in Kaohsiung’s Asia New Bay Area. Announced cluster capacity and utilization figures follow their individual source dates; they are not a live availability feed. The public information identifies the area, not an exact data hall or entrance.
100 MW is a two-phase supply plan: 30 MW planned for 2029-06-20, followed by an additional 70 MW on 2030-02-20. The owner’s latest update places the project at the power-application stage. The supplied 2026-07-31 Taipower letter includes validity, works, inspection and contract conditions; it is not proof of 100 MW currently available. Backup capacity must not be added to regular supply. Planned wind, solar, storage and gas facilities in the applicant’s concept are not verified assets or an achieved RE100 commitment.
MediaTek announced the opening of Phase 1 on 2026-05-07. News reports cite 15 MW for Phase 1 and 45 MW across three phases. The 45 MW plan includes Phase 1: do not add them or describe all 45 MW as operational. This is an internal R&D facility; external rental availability is unconfirmed.
Public acquisition records more strongly support the former Taiwan Imperial Tobacco facility at No. 8, Qunyi Road, Zhunan. The owner reports a power application; MW is undisclosed. A 2026-05-08 filing republication lists an NT$2.05 billion property transaction, and a 2026-09-11 report links the site to an AI data center plan. A separate 2026-09-09 report names Taiwan Tobacco and Liquor and NT$1.65 billion; these conflicting descriptions must not be merged. Existing Phison AI servers elsewhere are not equipment at this planned site.
The 30 MW figure and a location beside Dayuan Cogeneration come from the platform owner, who reports a power application. The power plant’s official address is only a surrounding-area reference. It does not verify the AIDC parcel, a partnership with the plant or approved capacity. Group-level AIDC news dated 2026-08-17 is background, not evidence for this site’s 30 MW.
The owner clarifies that this project is only at the power-application stage. The 100 MW scale is owner-reported; the application, reference number, approved capacity and energization schedule have not been checked against documents. The 2026-09-09 land-transaction reporting is background, not evidence of AIDC construction or operation. The former Wanyou paper site and the whole Beigang industrial park must not be treated as one completed data center.
The 3 MW scale and the relationship between Clouded Leopard and RITEK’s Hukou campus come from the owner, who reports a power application. The campus can be referenced publicly, but the actual building, partnership and GPU inventory are unverified. No independently cross-checked announcement links this site, Clouded Leopard and 3 MW together.
The 70 MW scale and conversion of the former Makro property come from the owner. The historical address is in Taibao, Chiayi County; the project stage remains unconfirmed. This is a separate record from FCFC’s 70 MW Xingang lead. The old factory registration confirms an address, not an AIDC conversion, capacity or current ownership. Historical logistics recruitment at the address requires further handover and occupancy checks.
The main card uses a 10 MW plan consistently reported by multiple sources on 2026-07-30 and in subsequent August coverage. A 2026-07-31 Economic Daily report separately cites 100 MW; no company document has resolved that discrepancy, so it is not labeled a confirmed typo. The owner reports a power application. Two-stage power delivery does not mean either or both stages are energized; stage-level MW and exact dates are undisclosed.
Existing buildings · Power availability under review
The owner reports a 70 MW development lead involving existing buildings at FCFC’s Xingang site, with power availability still being confirmed. Existing industrial supply or captive generation is not proof that 70 MW can be allocated to an AIDC. Reporting dated 2026-06-03 supports factory-space marketing for AI centers at Xingang and Longde, but not approved power for this specific lead. This is distinct from the 70 MW former-Makro project in Taibao.
Existing buildings · Power availability under review
The owner corrected this lead to 70 MW. It concerns existing buildings at FCFC Longde, with power still under review. Existing factory supply or captive generation does not establish AIDC approval, energization or rentable capacity. News supports asset-reuse background, not approval of 70 MW. Do not merge this record with other FCFC sites, Lize compute projects or on-site generating facilities.
Existing buildings · Power availability under review
The owner reports a 10 MW lead at existing buildings at CMFC Dashe, with power under review. Corporate AI-transition reporting is background and does not verify this capacity, a tenant or commercial operation. CMFC is not CPDC or another neighboring Dashe company. Existing industrial or cogeneration capacity must not be treated as available AIDC capacity.
Public reports link Tatung’s Taoyuan AI data center planning to its Dayuan factory and mention collaboration discussions and POC preparation. Capacity, power application, construction, energization and rental inventory are undisclosed. Reports dated 2025-11-10 and 2026-09-14 provide planning context. A factory registry status of operating concerns the existing factory, not the proposed AI data center.
Planning intelligence · Site and stage unconfirmed
Reporting dated 2026-09-14 confirms only a planned ASUS-owned AI data center in Taoyuan. A public address exists for the Luzhu factory, but the smart factory, AI LAB and proposed AI DC may be different facilities. The relationship requires official cross-reference. Capacity, the precise site and the power-procurement stage remain undisclosed.
CPDC plans to reuse its Toufen plant for AI compute. The 2026-09-17 MoneyDJ report gives 5 MW for Phase 1 and a 50–100 MW Phase 2 plan; Phase 3 scale is undisclosed. These are plans, not energized or rentable inventory. Collaboration is still being developed. Reported customer demand does not establish named buyers, signed contracts, equipment counts or opening dates. Existing feeders, generation and cooling do not prove power approval for the AIDC.
A public rental listing at No. 275, Section 1, Nankan Road advertises 3 MW of power and markets the property for AI compute. The owner identifies it as YFY’s Nankan campus. Historical directories support the YFY name, while current government factory records identify Chung Hwa Pulp at the address; ownership and power-contract responsibility are not resolved here. The 3 MW property claim is not verified IT load, energized AIDC supply or GPU inventory.
The project scale is 6 MW, with approximately 1 MW of cooperation with GMI Cloud, according to information supplied to the platform. These figures have different scopes and must not be added together. The partnership is public; reporting describes 72 HGX B300 systems, without confirming their full allocation to this factory or commissioning.
Public validation site · Commercial status unconfirmed
Giga Computing’s GAIFA in Tucheng is a compute and infrastructure validation site. Reported plans include 700 kW (0.7 MW) and six compute, storage and networking racks, with direct liquid cooling. GPU count, IT load, rental inventory and street address are undisclosed.
Provider-reported 9.9 MW project in Shengang, Taichung. A Taipower application has been submitted; approval has not been verified. Received on 2026-10-08; not independently verified. Total power and IT load are not separately disclosed.
Provider-reported 10 MW project in Neihu, Taipei. An unnamed Singapore company is constructing a five-storey building on its own land; power and commissioning status are undisclosed. Received on 2026-10-08; not independently verified. Total power and IT load are not separately disclosed.
Provider-reported 50 MW AIDC project in the Luzhu science park area of Kaohsiung. A power application is in progress. Power approval, site address and IT load have not been independently verified.
A provider reports an unnamed company obtained a 55 MW power-application outcome associated with Jiayi Substation in Pingtung. No Taipower document has been reviewed; approval terms and energization remain unverified. The suggested Daqing industrial area location is a provider hypothesis, not a confirmed site.
SoftBank acquired former Sharp property for an approximately 150 MW power-receiving plan, potentially expanding beyond 250 MW. A target date is not commissioning evidence; this is separate from KDDI’s Sakai project.
KDDI opened its Osaka Sakai AI facility on January 22, 2026, reusing Sharp facilities and deploying systems including GB200 NVL72. MW is undisclosed in this source; GPU cloud trials and applications follow separate schedules.
ABC reports local development approval for the 288 MW Bell Bay project. Firmus says energy arrangements remain to be finalized; approval is not energization or operation.
NEXTDC and OpenAI signed an MOU for an AI campus at S7 in Eastern Creek, Sydney. The announcement’s 550 MW potential capacity is not operational supply.
OpenAI confirms early training and inference at Abilene. Expansion plans are separate from existing operations; total Stargate capacity is not allocated to this campus.
Vantage announced four Lighthouse data centers in Port Washington, targeting close to 1 GW and completion in 2028. These are announced plans, not proof of current operation.
Groundbreaking ceremony held May 18, 2026; the city lists a June construction target and operation as early as February 2027. Operation is unconfirmed.
Candidate site with potential for a 1 GW-scale cluster, under tenant discussions. Not approved or operating capacity, and separate from the S2 proposal.
The current developer page lists construction and approximately 750 MW; January 2026 reporting cites 1.2 GW. Scope/basis reconciliation is pending; do not add the figures or treat them as rental inventory.
The September 2025 announcement confirms this site in the development program. Current commissioning is not verified; no allocation of aggregate Stargate capacity.
The September 2025 announcement confirms this site in the development program. Current commissioning is not verified; no allocation of aggregate Stargate capacity.
The September 2025 announcement confirms this site and groundbreaking. Current commissioning is not verified; no allocation of aggregate Stargate capacity.
The October 1 government update confirms construction of the 300 MW campus and four first-phase shells. First hall targets H1 2027; potential 1.2 GW expansion is not built capacity.
May 2026 announcement: targeted later in 2026. The over-150 MW goal for 2032 belongs to the three-site cluster, not this site. New commissioning evidence was not verified.
May 2026 announcement: targeted to open at end-2026 and scale through 2028. The over-150 MW goal for 2032 belongs to the three-site cluster, not this site. New commissioning evidence was not verified.
May 2026 announcement: targeted to come online in 2029. The over-150 MW goal for 2032 belongs to the three-site cluster, not this site. New commissioning evidence was not verified.
Final major build phase began in September 2026; campus total is planned at 90 MW and B2 completion targets Q2 2029. Not all campus capacity is complete.
Former power-station redevelopment near Blyth. QTS lists earthworks and first-building construction plans in 2026; subsequent work remains subject to permissions.
Stargate UK was reported paused in April 2026. This marker retains its announced Cobalt Park area and does not imply other facilities there stopped operating.
Construction announced March 20, 2026. The facility supports AI and enterprise workloads; retail capacity targets early 2028 using already allocated power.
Up to 1.44 GW planned IT capacity across four stages; development application under assessment. The developer cites an Anthropic lease commitment; capacity is not operational.
Resource consents obtained March 2026. 240 MW is IT capacity; the developer describes 280 MW total power consumption. Do not add them or equate consent with operation.
August 10, 2026 proposal explores 250 MW IT load near the retired TCC plant. Neither party has committed to construction; tenants, finance and approvals remain conditions.
Groundbreaking at Tarluvada on April 28, 2026. The gigawatt-scale hub comprises three campuses; this is one cluster anchor and does not duplicate aggregate capacity.
July 2026 announcement confirms construction, planned 1 GW and first delivery targeted in 2028. Meta is the initial sole occupant; not rental inventory.
Developer lists 245 MW contracted IT capacity supported by 330 MW utility capacity. Commercialization is not delivery; full commissioning is not verified from this page. An October 7 report confirms construction.
October 2026 report describes a filed preliminary plan for 36 buildings, phased from late 2026 toward 2036. The adjoining 4.5 GW power plant is not site IT capacity.
April 2026 proposal describes an initial 240 MW IT phase, potential 1 GW expansion and a 2032 target. Environmental studies remain ahead; marker illustrates the broad region south of Broome.
Two announced campuses together exceed 280 MW IT. One cluster marker avoids counting 280 MW per site or treating the four-campus 700 MW platform as fully operational.
First 40 MW phase topped out in August 2026 and remains under construction, with service now targeted for Q1 2027. Over 200 MW is the multiphase campus target.
September 2026 reporting identifies a conditional purchase of 221.665 acres for an AI-ready campus. It does not establish completed acquisition, construction or commissioning.
Developer describes CTP1/CTP2 under development with a 300 MW scale and a separate 1 GW power-platform ambition. A 2026 RFS target is not commissioning evidence.
Groundbreaking for a published 640 MW campus was announced September 22. September 30 reporting confirms a pause pending environmental and building approvals. Both milestones are retained.
March 2026 MOU and application describe an initial 50 MW and about 28,000 GPUs, targeting April groundbreaking. Actual subsequent groundbreaking is not verified here.
An August 28, 2026 LOI proposes 200 MW IT, with an initial 100 MW phase. Power arrangements and investment procedures remain pending; the event date is distinct from an unconfirmed publication date.
Government approval in July 2026 enables feasibility study and investment, announced in August. Site MW is undisclosed; the referenced 170 MW belongs to generation projects.
May 2025 MOU covers AI infrastructure feasibility and a potential 150-plus-hectare zone in the Vientiane capital area. It is not an approved or built data center.
Groundbreaking in November 2024; 20 MW and a Q1 2027 target. Marker represents the city-state only; district or premises are not verified from the primary source.