MEDIATEK TONGLUO R&D DATA CENTER

Partly operational · Phase 1 opened

MediaTek announced the opening of Phase 1 on 2026-05-07. News reports cite 15 MW for Phase 1 and 45 MW across three phases. The 45 MW plan includes Phase 1: do not add them or describe all 45 MW as operational. This is an internal R&D facility; external rental availability is unconfirmed.

Reveal on the map

Capacity & definitions

15 MW · 第一期新聞公布規模;三期合計規劃45 MW

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Industrial Lot 21, Tongluo Science Park, Miaoli, Taiwan; facility street number unverified

Approximate science-park reference, not a data hall entrance. Industrial Lot 21 was identified from the official June 2026 park map; no neighboring company’s street address is substituted.

Companies & roles (source language)

聯發科技 — 研發資料中心建置與使用方

NVIDIA — 運算平台供應商;不推定共同持股

Evidence, phases & discrepancies (source language)

部分營運:第一期已啟用;後續期別依需求推進,不能宣稱全45 MW已營運

第一期 · 已啟用 · 2026-05-07

第二、三期 · 依業務需求推進 · 2026-05-07 · 新聞報導兩期各15 MW;不得與45 MW再相加

公司公告支持啟用、研發用途及B200平台;15/45 MW另由新聞支持,兩者來源須分開顯示。

Original sources

  1. 聯發科:銅鑼研發資料中心正式啟用

    Source date:2026-05-07 · Checked:2026-09-15

    啟用、研發用途、DGX B200/DGX SuperPOD、三期規劃;不作15/45 MW的來源。

  2. Taipei Times:MediaTek資料中心啟用報導

    Source date:2026-05-08 · Checked:2026-09-15

    第一期15 MW、完整三期45 MW;不能解讀為全部45 MW已啟用。

  3. 新竹科學園區管理局:銅鑼園區配置圖

    Source date:2026-06 · Checked:2026-09-15

    已閱讀圖面;聯發科位於工21用地。檔名含2023,圖面更新日期實際為115.06。

  4. Mapcarta/OpenStreetMap:銅鑼科學園區南側工業用地

    Source date:— · Checked:2026-09-15

    園區參考點24.45527,120.75835;附近列聯發科。工21辨識另以官方園區圖為依據。

  5. 站長更新八案階段:聯發科部分營運;六案用電申請;嘉義另列待補充

    Source date:— · Checked:2026-09-15

    站長表示聯發科已有部分營運,並將嘉義算力另列,其餘通霄、群聯、雲豹大園、雲豹北港、雲豹錸德及緯創均在電力申請階段。嘉義算力的具體階段尚未說明,不自行推定已營運。

Record checked:2026-09-15

Translation does not constitute a new verification.