Bell AI Fabric Sherwood

Under construction

The October 1 government update confirms construction of the 300 MW campus and four first-phase shells. First hall targets H1 2027; potential 1.2 GW expansion is not built capacity.

Reveal on the map

Capacity & definitions

300 MW · 公開設施/規劃規模,非可出租庫存

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Saskatchewan · RM of Sherwood

Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.

Companies & roles (source language)

Bell — 公開來源所列參與公司;職責以原文為準

Evidence, phases & discrepancies (source language)

2026年10月1日政府確認300MW園區施工,首階段四棟建物成形,首機房目標2027上半年。潛在1.2GW擴展尚非建成容量。

來源日期所載進度 · 建置中 · 2026-10-01 · 2026年10月1日政府確認300MW園區施工,首階段四棟建物成形,首機房目標2027上半年。潛在1.2GW擴展尚非建成容量。

Original sources

  1. Government of Saskatchewan · 2026-10-01

    Source date:2026-10-01 · Checked:2026-10-09

Record checked:2026-10-09

Translation does not constitute a new verification.