AirTrunk JHB3 / JHB4 Cluster

Planned

Two announced campuses together exceed 280 MW IT. One cluster marker avoids counting 280 MW per site or treating the four-campus 700 MW platform as fully operational.

Reveal on the map

Capacity & definitions

280 MW · 公開設施/規劃規模,非可出租庫存

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Johor · Iskandar Puteri

Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.

Companies & roles (source language)

AirTrunk — 公開來源所列參與公司;職責以原文為準

Evidence, phases & discrepancies (source language)

兩新園區公告合計逾280MW IT;以群聚標記呈現,非各280MW,也不將四園區700MW全部當作營運。

來源日期所載進度 · 規劃中 · 2026-04-30 · 兩新園區公告合計逾280MW IT;以群聚標記呈現,非各280MW,也不將四園區700MW全部當作營運。

Original sources

  1. AirTrunk · 2026-04-30

    Source date:2026-04-30 · Checked:2026-10-09

Record checked:2026-10-09

Translation does not constitute a new verification.

Evidence methodology