TOKEN GROUND

AIDC / COMPUTE INTELLIGENCE

AWS Homer City Campus

Permit application

October 2026 report describes a filed preliminary plan for 36 buildings, phased from late 2026 toward 2036. The adjoining 4.5 GW power plant is not site IT capacity.

Reveal on the map

Capacity & definitions

— · 單站MW未公開/不推估

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Pennsylvania · Center / Blacklick Townships

Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.

Companies & roles (source language)

Amazon Web Services — 公開來源所列參與公司;職責以原文為準

Homer City Redevelopment — 公開來源所列參與公司;職責以原文為準

Evidence, phases & discrepancies (source language)

2026年10月報導提交36棟初步土地開發計畫,分期目標2026年底至2036年。鄰接4.5GW電廠不是本案IT容量。

來源日期所載進度 · 許可申請中 · 2026-10-06 · 2026年10月報導提交36棟初步土地開發計畫,分期目標2026年底至2036年。鄰接4.5GW電廠不是本案IT容量。

Original sources

  1. Data Center Dynamics · 2026-10-06

    Source date:2026-10-06 · Checked:2026-10-09

Record checked:2026-10-09

Translation does not constitute a new verification.

Evidence methodology