DDC1 Esbjerg
Under construction
Initial 11.5 MW phase broke ground, targeting October 2027; not live capacity.
Reveal on the mapCapacity & definitions
11.5 MW · 公開設施/規劃規模,非可出租庫存
Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.
Public location
Esbjerg · Port
Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.
Companies & roles (source language)
DDC1 Esbjerg — 公開項目名稱;參與方與角色以來源原文為準
Evidence, phases & discrepancies (source language)
首期11.5MW動工,目標2027年10月;不是已上線容量。
來源日期所載進度 · 建置中 · 2026-08-19 · 首期11.5MW動工,目標2027年10月;不是已上線容量。
Original sources
- Danish Data Center Industry · 2026-08-19
Source date:2026-08-19 · Checked:2026-10-09
Record checked:2026-10-09
Translation does not constitute a new verification.