DDC1 Esbjerg

Under construction

Initial 11.5 MW phase broke ground, targeting October 2027; not live capacity.

Reveal on the map

Capacity & definitions

11.5 MW · 公開設施/規劃規模,非可出租庫存

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Esbjerg · Port

Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.

Companies & roles (source language)

DDC1 Esbjerg — 公開項目名稱;參與方與角色以來源原文為準

Evidence, phases & discrepancies (source language)

首期11.5MW動工,目標2027年10月;不是已上線容量。

來源日期所載進度 · 建置中 · 2026-08-19 · 首期11.5MW動工,目標2027年10月;不是已上線容量。

Original sources

  1. Danish Data Center Industry · 2026-08-19

    Source date:2026-08-19 · Checked:2026-10-09

Record checked:2026-10-09

Translation does not constitute a new verification.