TOKEN GROUND

AIDC / COMPUTE INTELLIGENCE

MERLIN / EDGED Botorrita WIND

Planned

Planned 144 MW IT load targets H2 2029; strategic-investment designation does not equal all building permits.

Reveal on the map

Capacity & definitions

144 MW · 公開設施/規劃規模,非可出租庫存

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Aragón · Botorrita

Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.

Companies & roles (source language)

MERLIN / EDGED Botorrita WIND — 公開項目名稱;參與方與角色以來源原文為準

Evidence, phases & discrepancies (source language)

規劃144MW IT負載,取得戰略投資宣告不等於全部建築許可;目標2029年下半年。

來源日期所載進度 · 規劃中 · 2026-07-23 · 規劃144MW IT負載,取得戰略投資宣告不等於全部建築許可;目標2029年下半年。

Original sources

  1. MERLIN Properties · 2026-07-23

    Source date:2026-07-23 · Checked:2026-10-09

Record checked:2026-10-09

Translation does not constitute a new verification.

Evidence methodology