AIDC / COMPUTE INTELLIGENCE
Digital Edge / B.Grimm BKK1
Under construction
Groundbreaking took place in September 2025. May 2026 financing supports the 100 MW campus targeting Q4 2026 delivery; commissioning is not verified.
Reveal on the mapCapacity & definitions
100 MW · 公開設施/規劃規模,非可出租庫存
Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.
Public location
Chonburi · Eastern Economic Corridor
Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.
Companies & roles (source language)
Digital Edge — 公開來源所列參與公司;職責以原文為準
B.Grimm Power — 公開來源所列參與公司;職責以原文為準
Evidence, phases & discrepancies (source language)
2025年9月已動工;2026年5月取得280億泰銖綠色融資,100MW園區目標2026年第四季交付,尚未核實投運。
來源日期所載進度 · 規劃中 · 2026-05-07 · 2026年5月泰文官方公告取得280億泰銖綠色融資,開發100MW園區;融資公告本身不證明投運。
公開動工進度 · 建置中 · 2025-09-04 · 2025年9月已動工;2026年5月取得280億泰銖綠色融資,100MW園區目標2026年第四季交付,尚未核實投運。
Original sources
- B.Grimm Power · 2026-05-07
Source date:2026-05-07 · Checked:2026-10-09
- Digital Edge · 2025-09-04
Source date:2025-09-04 · Checked:2026-10-09
Record checked:2026-10-09
Translation does not constitute a new verification.