Digital Edge / B.Grimm BKK1

Under construction

Groundbreaking took place in September 2025. May 2026 financing supports the 100 MW campus targeting Q4 2026 delivery; commissioning is not verified.

Reveal on the map

Capacity & definitions

100 MW · 公開設施/規劃規模,非可出租庫存

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Chonburi · Eastern Economic Corridor

Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.

Companies & roles (source language)

Digital Edge — 公開來源所列參與公司;職責以原文為準

B.Grimm Power — 公開來源所列參與公司;職責以原文為準

Evidence, phases & discrepancies (source language)

2025年9月已動工;2026年5月取得280億泰銖綠色融資,100MW園區目標2026年第四季交付,尚未核實投運。

來源日期所載進度 · 規劃中 · 2026-05-07 · 2026年5月泰文官方公告取得280億泰銖綠色融資,開發100MW園區;融資公告本身不證明投運。

公開動工進度 · 建置中 · 2025-09-04 · 2025年9月已動工;2026年5月取得280億泰銖綠色融資,100MW園區目標2026年第四季交付,尚未核實投運。

Original sources

  1. B.Grimm Power · 2026-05-07

    Source date:2026-05-07 · Checked:2026-10-09

  2. Digital Edge · 2025-09-04

    Source date:2025-09-04 · Checked:2026-10-09

Record checked:2026-10-09