The owner corrected this lead to 70 MW. It concerns existing buildings at FCFC Longde, with power still under review. Existing factory supply or captive generation does not establish AIDC approval, energization or rentable capacity. News supports asset-reuse background, not approval of 70 MW. Do not merge this record with other FCFC sites, Lize compute projects or on-site generating facilities.
Reveal on the mapCapacity & definitions
70 MW · 站長提供規模;電力確認中,非已核准容量
Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.
Public location
No. 2, Longxiang 10th Road, Daxing Village, Dongshan, Yilan, Taiwan
Campus-level location only; actual buildings and the 70 MW power footprint are unconfirmed. The official address is in Dongshan while the open-map reference lies toward Su’ao; neither is asserted as a verified building entrance.
Companies & roles (source language)
台灣化學纖維股份有限公司/台化 — 既有龍德廠區相關方;新聞提廠房招商,AIDC營運/承租方未確認
Evidence, phases & discrepancies (source language)
既有建物,電力確認中;未核實AIDC投運
電力確認中與用電申請中不同。不能自行補成已申請、已受理、已核准、已送電或確定沒有電;現有工廠供電也不等於AIDC可用電。
站長已更正龍德規模為70 MW;公開新聞提龍德廠房招商AI資料中心,但沒有核定本案70 MW或證明AIDC可用電力。
不把本案與台化礁溪的其他廠區、利澤其他算力案或同廠自備發電設施合併。
既有工業廠區供電/自備電源不等於已有70 MW可供新AIDC使用,也不等於承租方已進場。
Original sources
- 站長新增三案:台化嘉義、台化龍德、中纖大社
Source date:— · Checked:2026-09-15
三案均為既有建物、電力確認中。容量是站長提供的案場規模;不是已核准容量、確定可供AIDC用電或可出租GPU庫存。
- 站長更正:台化嘉義與龍德兩案均為70 MW
Source date:— · Checked:2026-09-15
站長澄清龍德原先少打一個0,應為70 MW;嘉義台化維持70 MW,中纖大社維持10 MW。三案均為既有建物、電力確認中。
- 台化官方:公司廠區位置
Source date:— · Checked:2026-09-15
新港廠:嘉義縣新港鄉中洋村中洋工業區1號;龍德廠:宜蘭縣冬山鄉大興村龍祥十路2號。只支持廠區定位,不證明70/70 MW或指定建物可用電。
- MoneyDJ:台化COMPUTEX展出與既有廠房招商
Source date:2026-06-03 · Checked:2026-09-15
報導宜蘭龍德及嘉義新港既有廠房招商AI運算中心。文中自備電力敘述不能等同本清單的70/70 MW已分配、核准或送電給AIDC。
- OpenStreetMap:臺灣化學纖維龍德廠
Source date:— · Checked:2026-09-15
Nominatim取得龍德廠工業用地約略參考點121.815498,24.6273495。園區範圍與官方門牌所在行政區須分別保留,不當作AIDC入口。
Record checked:2026-09-15
Translation does not constitute a new verification.
Evidence methodology