Eni / Khazna AI Campus

Planned

Heads of terms propose a phased 500 MW IT campus, not completed financing, construction or commissioning.

Reveal on the map

Capacity & definitions

500 MW · 公開設施/規劃規模,非可出租庫存

Total power and IT load are different measures: do not add them. Published plans do not establish energized capacity, commercial operation or rental availability.

Public location

Lombardy · Ferrera Erbognone

Illustrative city, county or campus-area anchor from the publicly named locality, not surveyed premises, an entrance or a parcel. A listed public address does not make this marker an exact geocode.

Companies & roles (source language)

Eni / Khazna AI Campus — 公開項目名稱;參與方與角色以來源原文為準

Evidence, phases & discrepancies (source language)

合作條款規劃分期500MW IT園區;不代表已完成融資、建造或投運。

來源日期所載進度 · 規劃中 · 2025-07-11 · 合作條款規劃分期500MW IT園區;不代表已完成融資、建造或投運。

Original sources

  1. Khazna / Eni · 2025-07-11

    Source date:2025-07-11 · Checked:2026-10-09

Record checked:2026-10-09

Translation does not constitute a new verification.